Kamstrup project model

Phase 3: Production

 

Description 
During this phase the system components are produced in our factory and shipped to the installation site, OEM hardware and software is procured, installation, including training of installation personnel is planned in detail.

If development of software or hardware is required, development including test is carried out during this phase.


If a Factory Acceptance Test (FAT) has been agreed with the customer, necessary documentation for the FAT is prepared, and the FAT is carried through with the customer.


At the end of the Production Phase installation is ready to start. 

 

Results to be achieved during the Production Phase:

  • Projecting plan agreed
  • Contract regarding installation signed with sub-supplier
  • Shipment of equipment from factory is checked before dispatch
  • Installation planned and scheduled in detail
  • Factory Acceptance Tests (FAT) carried through (if relevant)
  • Installation documentation prepared
  • Installers trained
  • Components manufactured and received at installation site
  • Hardware and software for main station procured and delivered to site
  • Software development finalised including test
  • System Operation agreed and scheduled with customer 

The following templates and Check Lists are available in The Kamstrup CRM system and on the Intranet:

  • Check List for Production phase
  • Check List for FAT
  • Check List for Central System Production 